Jones company uses a job-order costing system with a predetermined overhead rate of 120% of direct labor cost. The job cost sheet for job #420 showed that jones company spent $4,000 on direct materials and $5,000 on direct labor on the job. What is the total cost of job #420?.

Answer :

Parrain

Based on the various costs of the job, we can calculate the total cost of the job to be $15,000.

What is the Overhead cost?

= Direct labor x 120%

= $6,000

Total cost of Job #420

= Direct labor + Direct materials + Overhead

= 5,000 + 4,000 + 6,000

= $15,000

In conclusion, the total cost is $15,000.