vhegg The company that you manage has invested $5 million in developing a new product, but the development is not quite finished. At a recent meeting, your salespeople report that the introduction of competing products has reduced the expected sales of your new product to $3 million. If it would cost $1 million to finish development and make the product, youshould go ahead and do so. The most you should pay to complete development is $2.0 million.

Answer :

Answer:

Yes; $2.0 million

Explanation:

Yes, YOU SHOULD GO AHEAD and do so reason been that the TOTAL LOSS would then be the amount of $3 million calculated as [( -$5million)+(-$1 million)+$3 million=-$3 million] instead of the amount of $5 million which therefore means that The MOST YOU SHOULD PAY in order to complete the development would be the amount of $2 million calculated as ($5 Million-$3 Million).