Answer :
Answer:
There is a Lower fixed cost of process A, So, until 2,000 units are not achieved ,the process A should be chosen as priority and above the 2,000 units, process B should be chosen.
Explanation:
Cross over point
= ( Difference in fixed costs) / ( Difference in variable cost per unit)
= ($20,000 - $8,000) / ($10 - $4)
= $12,000 / $6
= 2,000 units
As per the general rule of choosing, above the cross over point, the process with lower variable cost should be chosen and below cross over point, the process with lower fixed cost should be chosen
There is a Lower fixed cost of process A, So, until 2,000 units are not achieved ,the process A should be chosen as priority and above the 2,000 units, process B should be chosen
Answer:
2000units
Explanation:
Cost data
Fixed cost Variable cost
Process A $8000 $10
Process B $20000 $4
Supplier $0 $20
= (Difference in fixed expenses)/(Difference in factor cost per unit)
= ($20,000 - $8,000)/($10 - $4)
= $12,000/$6
= 2,000 units
According to the general guideline of picking, over the traverse point, the procedure with lower variable expense ought to be picked and underneath traverse point, the procedure with lower fixed expense ought to be picked
Lower fixed expense is of procedure A, So, till 2,000 units, process An ought to be picked or more 2,000 units, process B ought to be picked