The phases of project management are: A. planning, scheduling, and controlling. B. planning, programming, and budgeting. C. planning, organizing, staffing, leading, and controlling. D. different for manufacturing projects than for service projects. E. GANTT, CPM, and PERT.

Answer :

jafruevu

Answer:

A. planning, scheduling, and controlling.

Explanation:

The phases of project management are -

1. Initiation

2. Planning

3. Execution - Scheduling

4. Control

5. Close

Option A is correct because the answer includes the 2nd, 3rd, and fourth phases of project management.

Option B is wrong because programming is not a phase of project management. Option C is a combination of management functions. Therefore, it is incorrect. Option D is not correct as the service project is not different from the manufacturing project. Option E is the project management technique.